Project | : | Twin Pipe Laying (PHASE A’) |
Date | : | 31/1/2011 – 10/3/2011 |
Place | : | Al Mukalla Port – Yemen |
In January 2011 “POSEIDON” signed a contract with Messrs “MAM International Corp.” that was covering the “Underwater Installation of Twin Pipelines 310m long, diameter of 8’’ each”. This was part of the ‘‘Renewal of Oil C.B.M. Terminal Al Mukalla Installation’’. The whole project was successfully executed within 39 days and delivered to Messrs “MAM International Corp”.
Main works: Putting down concrete blocks, installing & bolting submarine pipelines to the concrete blocks and connecting them with riser pipelines.
.